Haircare Plant Capacity Increase

Project scope was to increase capacity by 60% in a haircare plant, touching: Packing, Making,Utilities, Shipping & Warehouse.

We led the project through definition & execution until start-up, by this contributing to best in class results. Scope was very complex, touching entire plant systems and involved all departments. Scope included: Modifications & Automation of Packing Lines, Process Water Treatment,  Waste Water Treatment, Palletizing and Warehouse, Materials Storage.

Zero safety Incidents, twelve months schedule achieved with minimal shut-down time, all volume transferred on time, 5 new technologies brought on site.